Rehabilitation of Ofankor – Nsawam Road (Dual Carriageway) 33.0km

Contractor:  Maripoma Enterprise Limited
Contract Sum:  GHS346,479,013.79 
Start Date:   23rd May 2022
Exp. Completion Date:   N/A
Current Progress:  70%
Agency:  GHA   Region:  Greater Accra / Eastern

The project has seen a significant progress since September of 2025 after government paid over $70 million in arrears to the contractor.