Ministry of Roads & Highways > Posts > Inspection > Reconstruction of Sunyani Road Phase II progresses steadily
Reconstruction of Sunyani Road Phase II progresses steadily
October 2, 2021
Inspection

Work is progressing steadily on the reconstruction of the Sunyani Road Phase II.
The project is expected to reduce traffic congestion on the N6 highway acting as an urban arterial, reduce travel time for the road users and residents along the corridor thereby contributing to the socio-economic development of the people.
The works started in October 2020 and its expected to be completed in September 2022. The Project is currently 16% complete.



These were disclosed by the Director Urban Roads, Ing James Amoo-Gottfried when the President visited the project site, this afternoon, as part of this 4-days working visit of the Ashanti Region.
Source: Ministry of Roads and Highways – PR Unit
Recent Posts
- Prez Mahama is Committed to Open-up Afram Plains once and for all” – Hon Agbodza
- Hon Agbodza inspects work on Buipe, Yapei Bridges
- Hon. Agbodza explores Partnerships with Local Banks to Fund Road Projects
- ROADS MINISTER INAUGURATES A 5-MEMBER COMMITTEE TO REVIEW ACTIVITIES OF AXLE LOAD OPERATION IN THE COUNTRY
- “We Will Prioritise Road Maintenance this year”- Kwame Agbodza
Categories
Tags
10-member Governing Board of the Ghana Highway Authority (GHA)
Abolishment of Road Tolls
Afram Plains
Bawku
Bawumia
Bolgatange
Bridge
Buipe
Buipe Bridge
Cessation of Road and bridge toll
Commissioning
Contractors
Dompoase Junction-Aputuogya Road
Dualization
Eastern Region - Roads
Expression of Interest
Floods
Funding
Inner Ring
Jasikan
Kaneshie
Kumasi
Lake Road Extension Project
Nana Akufo-Addo
Nyankomase-Assin-Jakai roads
Ohwimase-Twedie Road
Oti Region
Pokuase Interchange
Polimakom
President Akufo-Addo
Project Inauguration
River Oti
Road Safety Report
Road Tolls
SONA
Stakeholders
Tamale Interchange
Toll Collection
Transport Sector Review Conference
TSIP
Twifo Praso
Upper West Floods
Veep
Vice President
Yendi
Recent Comments